more info News & events more info Headquarters more info Contacts more info Language
         
 
 
= PRODUCTS & SERVICES =
      novec 1230 system
      cold fire systems
      fm-200 systems
      hfc-23 systems
      naf s-III systems
      argonite systems
      foam systems
      halon's bank
      water mist systems
      halogl IIB systems
      vesda systems
      extraction units
      powder systems
      vaporisers
      HFC-23TM
      gl-125TM
      gl-227TM
      engineering support
   fire safety
   halon
   motormax
   cold fire
   inergen
= CLEAN AGENTS =
MARINE FIRE SOLUTIONS
= RESERVED TO =
   companies
   schools

 

 
ENGINEERING SUPPORT
 
It is vital to the effectiveness of a gaseous fire-fighting system that it is constantly maintained at peak performance. 

If in an emergency the system is called upon to discharge, it is of critical importance that the concentration of the gas, and the length of time it is retained in the room, are both at the originally specified level.
  
 

 
 
ISO 9001 – ISO 14001 ACCREDITATION:
 
GIELLE Fire Engineering is accredited to ISO 9001 and LPS 1204 for the design, supply, installation and commissioning of gaseous extinguishing systems. Years of experience have proved that the engineering and documentary support – provided by GIELLE throughout every contract – are vital parts of the overall service. Indeed, the company is quite possibly unique among installation companies in the world in several respects. Its level of investment in state-of-the art computer equipment is rarely found in all but the largest fire safety companies, enabling GIELLE to respond quickly at the design and costing stage as well as throughout the contract.
 
SITE SURVEY:
 
Work on every project begins with a site inspection and the completion of an operational method statement, or with the completion of detailed site survey documentation. This ensures that every aspect of the project is co-ordinated and that installation is efficient and trouble-free. GIELLE also provides verification to show that the proposed installation parameters are in full accordance with the initial design.
 
FLOW CALCULATIONS & DESIGN DRAWINGS:
 
Once cylinder locations and pipework routes have been decided upon, every multi-nozzle system is hydraulically calculated. This confirms compliance with the concentration and discharge time requirements of the relevant standards.

Prior to installation, CAD-generated system layout and pipework isometric drawings are produced and submitted for approval. In the case of FM-200 and Argonite this is undertaken using the company’s in-house hydraulic calculation and design capabilities, meaning that any on-site changes that become necessary during installation are implemented without delay. This ensures that installed system retains its essential design integrity.
 
CERTIFICATE OF CONFORMITY: 
 
On final completion of the work, detailed “as-installed” drawings are issued by GIELLE to the customer, along with the appropriate commissioning and conformity certification required by LPS 1204.
 
 
send us an email

 info@gielle.it
* send us a fax 

 +39 080.3101309
call us  

 +39 080.3118998
 
 
Gielle Srl - Administrative Headsquares  
Via R. Ferri 32 Z.I. - 70022 Altamura (Ba) Italy
Tel +39 0803118998 - Fax + 39 0803101309
E-mail: info@gielle.it - Save in outlook
Free Number
 
 
 
Website of Gielle Group - Privacy - © 2009 Gielle Srl - created by www.omnilink.it